Yes. USPS originally expected its new Next Generation Delivery Vehicles (NGDVs) on carrier routes in late 2023, but the first production electric NGDVs did not begin serving routes until September 2024. The USPS Office of Inspector General later said the custom-vehicle selection, acquisition and deployment process ran about six years longer than the Postal Service’s initial schedule.
How far behind schedule are the USPS electric trucks?
The clearest comparison is between USPS’s April 2022 forecast and the first production vehicles entering service. In testimony to Congress, USPS said NGDVs were expected to begin appearing on carrier routes in late 2023. The USPS Office of Inspector General (OIG) reported that production electric NGDVs began serving routes in September 2024—roughly nine months after that public expectation. The OIG’s broader retrospective assessment was that the custom-vehicle selection, acquisition and deployment process took about six years longer than USPS’s initial deployment schedule. USPS OIG and USPS testimony, April 2022
Those measures describe different things: the nine-month comparison is against the publicly stated expectation for vehicles to appear on routes; the six-year figure is the OIG’s assessment of the overall process against USPS’s initial deployment schedule. They should not be treated as competing estimates of one precise delay.
What has USPS delivered—and what do the fleet numbers mean?
Counts vary by date and by what is being counted. USPS fleet updates combine custom NGDVs with commercial off-the-shelf electric vans and other vehicles, so the larger fleet totals are not NGDV-only delivery figures.
#1 Best Overall
- REAL USPS MAIL TRUCK FUN: USPS mail delivery truck with a mail slot, opening rear door, and cool features like working headlights and a horn. Sits one rider between the ages of 3 and 5, max weight of 60 lbs.
- MUSIC AND LIGHTS INCLUDED: Kids can enjoy their favorite tunes with the FM radio/MP3 player while the working headlights brighten up their playtime adventures
- SAFE DRIVING ADVENTURE: Equipped with foot pedal acceleration, this toy allows forward and reverse movements at a safe speed of 2.5 MPH, perfect for young drivers
- SMOOTH RIDES EVERY TIME: Power Trax traction strip tires ensure a steady, smooth ride, and the included rechargeable battery means the fun never has to stop for long
- EVERYTHING INCLUDED FOR FUN: Comes with a mailbox, 3 play envelopes for realistic mail adventures, plus a 6-volt rechargeable battery and wall charger for endless play
| Measure | Reported figure | What it counts |
|---|---|---|
| Electric NGDVs in service through May 2025 | 134 | OIG fleet-system data for electric NGDVs specifically. USPS OIG |
| Electric NGDVs planned by FY2028, in OIG’s May 2025 table | 43,500 | OIG’s table using USPS fleet-system data through May 2025. USPS OIG |
| Electric NGDVs in USPS’s later plans | 45,000 | USPS’s December 2025 update and May 15, 2026 fact page. The reviewed sources do not explain why this differs from the OIG’s earlier 43,500 figure. USPS Employee News; USPS fact page |
| Battery-powered vehicles on the road as of December 2025 | 8,500 | A broader modernization-fleet count, not electric NGDVs alone. USPS reported more than 35,000 new vehicles on the road overall. USPS Employee News |
| NGDV orders as of December 31, 2025 | 51,500 | Orders reported by Oshkosh, not vehicles delivered or placed in service. Oshkosh SEC filing |
USPS’s May 15, 2026 fact page described a plan for 106,000 new vehicles, including at least 66,000 battery-electric vehicles: 45,000 electric NGDVs and 21,000 commercial off-the-shelf electric vehicles. USPS fact page The latest reviewed source does not establish a verified NGDV-only in-service total as of October 4, 2026.
Why are the new USPS electric mail trucks delayed?
A custom vehicle takes longer to bring into production
The NGDV is a purpose-built, right-hand-drive delivery vehicle. The OIG said it took more than six years to select a supplier and more than three years from contract award to the first production vehicles. By contrast, USPS acquired commercially available Ford E-Transits in about one year. That comparison illustrates the longer path involved in developing and deploying a custom vehicle; it does not prove that any single procurement step caused the delay. USPS OIG
Rank #2
- 📬 Authentic Replica: 1:36 scale die-cast metal model of the iconic 1987 United States Postal Service (USPS) mail truck.
- 📬 Realistic Details: Features pull-back action, opening doors, and a rear sliding gate for added play value.
- 📬 Compact Size: Measures approximately 5 inches in length, making it a great desktop or display piece.
- 📬 Educational Toy: Introduces children to the postal service and encourages imaginative role-play.
- 📬 Collectible Item: A must-have for USPS enthusiasts and die-cast vehicle collectors alike.
Oshkosh says the production ramp took longer and cost more
Oshkosh’s January 2026 filing states that the NGDV production ramp took longer and cost more than the company anticipated. It identifies equipment-design issues, supplier quality and performance, and the challenge of scaling production as risks that could continue to affect output. The filing does not quantify how much each factor contributed to the delay. Oshkosh SEC filing
USPS characterized the rollout differently in a December 2025 update: fleet management senior director Justin Glass said, “The new fleet rollout is proceeding well, aligned with our plan.” That is the agency’s assessment of its broader fleet rollout; it does not change the OIG’s retrospective schedule comparison or turn aggregate fleet counts into NGDV delivery totals. USPS Employee News
Rank #3
- 📦 📬 AUTHENTIC DETAILS: Die-cast metal replicas featuring accurate UPS Mercedes-Benz Sprinter and USPS mail truck designs with detailed logos and markings
- 📦 📬 PREMIUM QUALITY: Constructed with durable die-cast metal and plastic parts for long-lasting play value and collectibility
- 📦 📬 PERFECT SIZE: Each vehicle measures approximately 5 inches in length, ideal for display or hands-on play
- 📦 📬 DUAL PACK VALUE: Set includes two iconic delivery vehicles - the modern UPS Sprinter van and classic USPS Grumman LLV mail truck
- 📦 📬 MOVING FEATURES: Both vehicles feature rolling wheels and opening doors for interactive play experience
When will USPS get the rest of the electric trucks?
USPS’s stated target is 45,000 electric NGDVs as part of its broader plan for 106,000 new vehicles. The agency’s May 2026 fact page says at least 66,000 of the planned vehicles will be battery-electric, split between 45,000 NGDVs and 21,000 commercial off-the-shelf EVs. These are plans, not a confirmed delivery timetable for each truck; the sources reviewed do not provide a current NGDV-only delivery schedule or a verified October 2026 service count. USPS fact page
Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.Why the NGDV is not the whole USPS electric fleet
USPS’s fleet program includes two distinct kinds of electric delivery vehicle:
Rank #4
- 📬 2.5 Inches 1:72 Scale
- 📬 Die Cast Metal
- 📬 Official USPS LLV Grumman
- Electric NGDVs: purpose-built, right-hand-drive vehicles designed for postal delivery.
- Commercial off-the-shelf EVs: existing models, including Ford E-Transits, acquired for postal use.
The distinction matters when reading progress reports. A figure for all battery-powered vehicles, all new vehicles, or NGDV orders cannot be used as the number of electric NGDVs actually serving routes. The OIG’s 134 figure is explicitly electric NGDVs in service through May 2025; USPS’s 8,500 figure is battery-powered vehicles across the broader fleet as of December 2025.
Quick Recap
Best Value
- HOBBY MODEL KIT – Unassembled model packed in an envelope with easy to follow instructions. Ideal for ages 14 and up.
- NO GLUE OR SOLDER NEEDED – Parts can be easily clipped from the metal sheets. Tweezers are the recommended tool for bending and twisting the connection tabs.
- USPS LLV MAIL TRUCK - 2 Sheet Model with a moderate difficulty level. Assembled Size: 2.99 L x 1.42 W x 1.50 H inches. 1:59 Scale.
- FROM STEEL SHEETS TO 3D – Pop out the pieces and connect using tabs and holes. Includes illustrated instructions.
- HIGHLY DETAILED ETCHED MODEL – Display your 3D model once completed - collect and build them all.
Product prices and availability are accurate as of the date/time indicated and are subject to change. Any price and availability information displayed on Amazon at the time of purchase will apply.
Quick wins for a faster PC:
Fix the driver behind crashes, sound loss and screen glitchesFind Drivers →Repair Windows errors before they cause bigger problemsFix Now →Scan for outdated or missing drivers - takes under a minuteDriver Scan →