Neoen says construction has begun on Stage 1 of the Goyder North Wind Farm, a 346 MW project near Burra in South Australia. The stage is planned to include 48 Vestas turbines, with operation expected in 2029.
What is being built at Goyder North?
Stage 1 is the portion now entering construction: Neoen’s October 2026 update gives it a capacity of 346 MW and a planned turbine count of 48. The project is part of the wider Goyder Renewables Zone in South Australia’s Mid North, near Burra, on lands the project identifies as Ngadjuri Country. Neoen’s October 2026 project update and its current Goyder North project page describe the stage and its location.
Who is building it, and how will it connect?
Neoen names Vestas as the wind farm contractor, including turbine supply, and Downer as the contractor for the overhead transmission line. The South Australian government identifies ElectraNet’s existing Bundey substation as the grid connection point. Neoen’s update and the government announcement provide those project details.
When is it expected to operate?
Neoen expects the wind farm to be operating in 2029, with crews expected on site from November 2026. These are the company’s announced schedule expectations, not confirmation of a completed commissioning date. Neoen’s October 2026 update sets out that timeline.
#1 Best Overall
- Metal Card Holder
- Wind Turbine Design with smooth spinning blade
- Product size: 5-1/2” x 3-3/4” x 1-3/8”
How does the BHP agreement fit?
Neoen has a 100 MW renewable energy baseload agreement with BHP for its South Australian mines, due to begin in July 2029. Neoen says supply will combine Goyder North generation with storage from Goyder Battery. This is a firmed supply arrangement; it does not mean wind from Goyder North alone will deliver a constant 100 MW or that a physical 100 MW flow will come directly from this wind farm at every moment. Neoen’s 24 September 2025 release describes the agreement and its intended start.
What are the local employment and accommodation estimates?
Neoen’s October 2026 update estimates around 500 jobs during construction and more than 10 ongoing operational roles. It also proposes temporary accommodation for approximately 300 workers across two locations, intended to reduce pressure on local housing. Those figures are estimates and a proposal, not realized job totals or completed accommodation. The update also says local supplier and jobseeker workshops are planned. Neoen’s project update contains these estimates and plans.
Rank #2
- FIFTH-GENERATION WIND TURBINE KIT: Updated version of the best-selling STEM kit about wind power and energy, kids can make their own wind turbine to explore this renewable energy source.
- OPTIMIZED FOR INDOOR & OUTDOOR USE: Design includes a new blade hub and gear ratio to enhance performance in outdoor wind and with indoor fan setups.
- WHAT YOU LEARN: Dive into the technology behind one of the most promising sources of clean energy, how it has been used it the past, and how it is used today.
- INCLUDES ELECTRIC MODEL CAR: Use your turbine to generate and store electricity to power a model car in just two minutes—no batteries required!
- GUIDED JOURNEY THROUGH WIND POWER: The 32-page, full-color manual provides illustrated step-by-step assembly instructions and easy-to-understand explanations about the scientific concepts at work.
Why do some sources give larger capacity figures?
Goyder North’s wider planning history is not the same scope as the stage now being built. The current project page says the wider project received planning consent for up to 135 turbines and approximately 1,000 MW, but that it has since been refined and Stage 1 is 346 MW. A federal referral summary describes an earlier Stage 1 proposal of up to 92 turbines and approximately 600 MW, as well as a proposed battery and alternative transmission-line routes. Those older figures describe earlier design assumptions; they are not the current construction configuration. See the current project page and federal referral summary for the distinct scopes.
Quick Recap
Best Value
- Realistic Wind Turbine Model: This wind turbine model toy mimics a real wind turbine to scale, and the most interesting thing is that its blades can also turn.
- 21.65inch Large Size Model: Compared to other ordinary wind turbine models, this wind turbine model has a large size, which can be installed up to 55cm/ 21.65inch.
- Wind-up Wind Turbine: This windmill toy adopts wind-up design that enables the blades turn automatically after it gets winded up. To wind it up, we just need to turn its blades clockwise for several rounds.
- Learn While Playing: This model of a wind turbine is not only a toy, but also a scientific and educational tool. It can guide children to understand the role of wind and inertia more intuitively, and cultivate children's interest in science.
- Suitable for Multiple Occasions: Kids can play with this windmill toy on their own or DIY transform it in the company of their parents. Teachers can also use it as an improvised teaching tool in the classroom.
Rank #4
- Build and experiment with a real, working 3-foot tall wind turbine to learn how wind is one of the most promising sources of clean, renewable energy available today.
- Single-piece blade construction for improved durability and better aerodynamics.
- Generate electricity to charge a battery and power a small model car.
- New weatherproof battery box can be left outside!
- Includes stakes to secure the turbine to the ground.
Rank #3
- Material: ABS engineering plastics;Net weight: approx. 147g
- A great replica of a Wind Powered Turbine, which is powered by sunlight shining on a solar panel in the base.
- It is a great desk model for an executive or an educational item to assist children understands the change between Solar Power and wind power.
- It is a great gift for your child, for your friend, for your client, and everyone who is interested in this product.Easy assemble. No glue required, No battery required.
- What's You Get: 1 x Solar Powered Rotating Base,1 x Tray,1 x windmill
Product prices and availability are accurate as of the date/time indicated and are subject to change. Any price and availability information displayed on Amazon at the time of purchase will apply.
The Tool Desk
Outbyte PC Repair FREERepair Windows errors before they cause bigger problemsFix Now →Outbyte Driver Updater FREEScan for outdated or missing drivers - takes under a minuteDriver Scan →